Postponed: New CCG Section Opening

We are disappointed to advise that the proposed opening of the new Connswater Community Greenway section from Beersbridge Rd to Grand Parade on Saturday 8th October has been postponed. This has been due to the late delivery of a handrail component to the contractor. As safety is our priority it is critical that this element is completed prior to opening.

The delay will allow the full section including the three new bridges to be opened on Saturday 22nd October 2016. We have received both an apology from the contractor for this delay and confirmation that the section will be ready to open 2pm on Saturday 22nd October 2016.

Providing a high quality, safe Connswater Community Greenway for all users is our priority and we thank you for your continued patience and support.